Symptom

When you add warranty information in the product master data under the sales Sheet, an error occurs.

"Value conversion missing or incomplete; complete remaining tasks"

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Product Portfolio work center
  2. Select By Materials view
  3. Search for Material ID
  4. Go to Edit
  5. Go to View all in right corner
  6. Select tab Sales, here you can maintain its warranty

Below are the steps to update warranty in the template

  1.Go to Business Configuration workcenter
  2.Go to Overview view.
  3.Select all activities
  4.Search the activity Migration of materials
  5.Click on -You can also, option in the right corner
  6.Download migration template
  7.Add details under Warranty in downloaded migration template
  8.Save and upload
  9.Click on Properties and select enhance already existing records
 10.Execute migration step by step
 11.validate file

Error appears "Value conversion missing or incomplete; complete remaining tasks"

Cause

The cause for the issue is that, value conversion is not maintained

Resolution

When you add Warranties, maintain the value conversion manually by following the steps:

1. In the error log screen click on line Value conversion missing or incomplete

2. Go to convert values

3. Select each line

3. Go to Process task

With the help of value help, maintain value which the system is taking.

For instance, value conversion E = Eng (English) is required.