Symptom
Error CK466 when creating material cost estimate or making order confirmation:
"No price could be determined for internal activity xxxx xxxx".
Environment
SAP S/4HANA Cloud Public Edition
Cause
Make sure the cost rate has been maintained correctly in app Manage Cost Rates - Plan.
If it is only maintained in Company Code currency, consider the exchange rate between company code currency and group currency.
Since if a small value is maintained in company code currency, when converting to group currency, the value may be rounded to zero.
Resolution
Increase the price unit to overcome this issue.
Keywords
CK 466, error, confirmation, cost estimate, CK11N, CO11N, Perform Maintenance Job. , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , CO-OM-ACT-2CL , Activity Types (Public Cloud) , Problem