Symptom
You meet error CK466 when creating material cost estimate or making order confirmation:
"No price could be determined for internal activity xxxx xxxx".
Environment
SAP S/4HANA Cloud
Cause
Please make sure you have maintained cost rate correctly in app Manage Cost Rates - Plan.
If you only maintained in Company Code currency, you need to consider the exchange rate between company code currency and group currency.
Since if you have maintained a small value in company code currency, when converting to group currency, the value may be rounded to zero.
Resolution
You can increase the price unit to overcome this issue.
Keywords
CK 466, error, confirmation, cost estimate, CK11N, CO11N, Perform Maintenance Job. , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , CO-OM-ACT-2CL , Activity Types (Public Cloud) , Problem