3255163 - How to schedule dependency background job using the program BTC_EVENT_RAISE

Symptom

When you schedule two jobs with a predecessor-successor relationship (start condition "Start after job"), you can schedule the predecessor periodically, but not the successor. The BTC_EVENT_RAISE program is now available to solve this technical problem.


Read more...

Product

SAP NetWeaver 7.0 ; SAP NetWeaver 7.1 ; SAP NetWeaver 7.2 ; SAP NetWeaver 7.3 ; SAP NetWeaver 7.4 ; SAP NetWeaver 7.5

Keywords

BTC_EVENT_RAISE, SAP_END_OF_JOB, Start after job, SM62, SM64, dependency, predecessor, sucessor, periodically, after job, sequence, completion, triggered , KBA , job chains , BC-CCM-BTC , Background Processing , How To