Symptom
You use MRP to plan your requirements.
One or more of the following symptoms are observed:
- It's not possible to convert multiple planned orders created via MRP into only purchase requisition.
- It's not possible to generate one single purchase requisition for different materials through MRP.
Environment
SAP S/4HANA Cloud, Public Edition.
Cause
Standard System Behavior.
Resolution
In SAP Standard, it's not possible to have Single PR for Multiple Items through MRP.
MRP will always generate purchase requisitions for only one material.
Keywords
MD15, MD01, MD02, MD03, MD01N, SKU, 1, MORE, CONVERT, ME53, ME53N, ME22, ME22N, ME21N, MRP RUN, Schedule MRP, Cloud. , KBA , PP-MRP-2CL , Material Requirements Planning (Public Cloud) , Problem