SAP Knowledge Base Article - Public

3265749 - Calendar tasks do not update when Daylight savings time changes

Symptom

Calendar tasks do not adjust their execution based on Daylight savings time changes.

A task scheduled to execute at 9:00 will execute at 8:00 or at 10:00 depending on in which direction the time changes occurs.

Environment

SAP ANALYTICS CLOUD all versions

Cause

Calendar tasks are scheduled based on invariant GMT time. 

As such the tasks are not adjusted due to DST changes.

Resolution

As this is the current design of calendar tasks there is no workaround or solution other than recreating the calendar tasks if the change in execution time negatively impacts business processes.

Keywords

DST, Daylight Savings Time, Calendar, Calendar tasks. , KBA , LOD-ANA-PL , Planning , Problem

Product

SAP Analytics Cloud 1.0