Symptom
Responsible cost center maintained for a WBS element is not used during Postings for Statistical Project.
Environment
SAP S/4HANA Cloud
Cause
During postings the cost center maintained in the field 'Responsible Cost Center' for the WBS element is not used. Rather, the cost center maintained in the field 'Default Cost Center for Postings' in the control tab of the app 'Project Control' is used.
Resolution
The cost center to which the postings is to done should be maintained in the field 'Default Cost Center for Postings'.