Symptom
While converting Purchase Requisition to Purchase Order in app Process Purchase Requisitions V2 for 2 different plants, only 1 Purchase Order is being created.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open app Process Purchase Requisitions V2.
- Select 2 PR's with same supplier but different plants.
- Click on Create Purchase Order option.
- Only one PO is being created for the two PR's.
Resolution
Multiple Purchase Orders cannot be created by selecting the Purchase Requisition Items. It is necessary to select Purchase Requisition Items with same supplier, Purchasing Organization and Purchasing Group to create the Purchase Order.
See Also
Keywords
Process Purchase Requisitions, Different Purchase orders, Purchasing Group, Plant, different plant, same supplier, PR individually, creation of PO, Create Purchase order, convert to PO from PR, S4_1C, S4HC, X4BX, S4_PC , KBA , MM-FIO-PUR-REQ-SOC , Fiori UI for Sourcing Purchase Requisitions , Problem