Symptom
- A BW Process Chain is triggered by /CPMB/TRIGGER_BW_CHAIN.
- If the BW Process Chain is executed directly in BW, some processes are executed parallelly but when it is executed by BPC Data Package, these processes are executed sequentially, which enlarges the overall execution time.
Environment
SAP BusinessObjects planning and consolidation 10.1, version for SAP NetWeaver(BPC 10.1 NW).
SAP Business Planning and Consolidation 11.0, version for SAP BW/4HANA.
SAP Business Planning and Consolidation 11.1, version for SAP BW/4HANA.
Cause
A BPC parameter is missing.
Resolution
Set the parameter "TRIGGER_BW_CHAIN_ASYNC" in SPRO in the backend BW system according to the Note 2151670.
Keywords
KBA , EPM-BPC-NW , NetWeaver Version , EPM-BPC-BW4 , BPC/4 , Problem
Product
SAP Analytics Cloud 1.0