3301274 - List Price not Considered While Creating Project Purchase Request

Symptom

You have created a List Price for a service item. However while creating project purchase request for the service item, system determines incorrect price.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Project Management work center
  2. Go to Projects view
  3. Select the relevant Project
  4. Select Edit and go to Products tab
  5. Select the relevant Service
  6. Select Create Project for whole task
  7. Price gets populated
  8. Click on Submit button
  9. System creates a Purchase Request
  10. System did not copy the Price from list price

Cause

You have created a list price in different currency and hence you see a different value when system creates purchase request from project. When you do the currency conversion between two currencies, the value is same.

Resolution

If you want system to capture the same pricing value, make sure that List Price currency and Project Purchase Request currency is same. If it is different, you have to perform currency conversion and calculate the prices.

Keywords

Price from Project Purchase Request not carried to Purchase request; price in Project Purchase Request; , KBA , AP-PRP-PR , Purchase Request , Problem

Product

SAP Business ByDesign 2211 ; SAP Business ByDesign 2302 ; SAP Business ByDesign 2305