Symptom

The condition type PCIP holds Future Price from Material but Standard Price is expected.

Reproducing the Issue

  1. Create Sales Order
  2. Enter a material line item
  3. Press Enter
  4. Check PCIP condition type
  5. The value is from Future Price rather than Standard Price

Cause

If the Future Price in material is available and valid, the Future price will be considered as Cost (Internal Price) instead of Standard Price.

Resolution

Make sure the Future Price is always valid for the customer's business and then the right Cost value will be read by SD Pricing module.