3314843 - System Not Releasing Production Proposal To Production Request Automatically.

Symptom

You want to know why system is not releasing production proposal automatically though required scoping question is scoped. However system displays below errors:

Cannot request production proposal start date out validity period

Exceptions
Proposal Outside Validity Period
Start Date in Past

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Planning workcenter.
  2. Go to Products view.
  3. Search required Product ID with planning area.
  4. Select and choose Open button.
  5. Under Supply and Demand, you find the Production Proposal is not released..
  6. Select and Open required Production Proposal, you see that under exceptions tab below exceptions.
  • Proposal Outside Validity Period
  • Start Date in Past

Cause

Since the corresponding Bill Of Material's Valid From date maintained is later than the Start Date of Production, or Valid To date is earlier than the Start Date of Production, system is not creating production requests.

You can check Start and End Date in relevant Production Proposal ID along with BoM Validity Period From/To.

Resolution

  1. Go to Planning and Production Master Data workcenter.
  2. Go to Production Bill Of Materials view.
  3. Find the relevant BoM ID.
  4. Edit and update the BoM ID as per business requirement.
  5. Or you can create a new BoM for it.
  6. Once the required changes are done, check and release the relevant Production Model again to reflect required changes in proposals.

See Also

Keywords

Production proposal,  Bill Of Material's Valid From, cannot request production proposal start date out validity period, Proposal Outside Validity Period, Start Date in Past, exceptions , KBA , production proposal , proposal outside validity period , start date in past, , exception , bill of material , SRD-SCM-WME-PRD , Production Control , Problem