Symptom
Actual finish date is not appearing at project task level.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project Management work center
- Go to Projects view
- Search for the relevant Project
- Status of project is "Closed"
- Choose the relevant Task
- Navigate to Scheduling Tab
- You can see Actual Dates
- The finished date appears blank
Cause
The "Finish Date" field is not applicable at the task level, as per the current system design.
Resolution
The "Actual Finish Date" at the project task level is manually editable by the Project Manager and is not automatically set by the system.
If you wish to populate this date automatically, it can be achieved through a PDI solution. The date field is available for PSM (Public Solution Model) write access. For implementation, please reach out to your partner development team.