Symptom
Actual finish date is not appearing at project task level.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project Management work center
- Go to Projects view
- Search for the relevant Project
- Status of project is "Closed"
- Choose the relevant Task
- Navigate to Scheduling Tab
- You can see Actual Dates
- The finished date appears blank
Cause
Finish date does not apply at task level and system is working as designed.
Resolution
The actual finish date on the project task level is editable by the project manager. There is no logic to set it automatically by the system.
In case if you want to define the actual finish date on the project task level automatically, then it can be done via a PDI solution. The date field is released for PSM write access and contact your partner development team.
See Also
Keywords
Actual Start/Finish dates; Project task level dates; Actual dates , KBA , project task level dates , actual start/finish dates , actual dates , AP-PRO , Project Processing , How To