3318181 - It's not clear why WIP is still being calculated although DLV/TECO is set

Symptom

You have set status DLV or TECO for production order. You expect the order WIP should be canceled and Variance should be calculated. However, you find WIP is still being calculated for the production order.

Environment

SAP S/4HANA Cloud Public Edition

Cause

Whether WIP is calculated or not is determined by the date when status DLV or TECO is set. If both status is set, DLV has higher priority.

For example if the date is set in period 2, if you check data in period 1, there will be WIP calculated.

Resolution

You can check the date of the status via below steps:

  1. Open app Display Production Order, and input order number.
  2. Click into detail view and click the status button.
  3. Choose status DLV or TECO.
  4. Click Menu - Extras - Chang Documents - For Status.