Symptom
Explain how the system prioritizes the selection of Production Version in Standard Cost Estimate
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Execute costing in app "Create Material Cost Estimate" (CK11N).
- Go to Qty Struct. tab.
- Check the Production Version.
Resolution
The strategies for selection of a production version in costing are as below:
-
The system uses the production version that was entered in the material master Costing View 1
-
The system uses the production version that is specified in the settings for the quantity structure control in the BOM
-
If none of the above strategies can be used, the system selects the production version with the latest validity date
See Also
Keywords
CK11N, Production Version, BOM, Costing, Cost Estimate, Quantity Structure, Master Data , KBA , CO-PC-PCP-WQS-2CL , Product Costing with Quantity Structure (Public Cloud) , CO-PC-PCP-WQS , Product Costing with Quantity Structure , How To