SAP Knowledge Base Article - Public

3321471 - Priority sequence for Production Versions in Costing

Symptom

Explains how the system prioritize the selection of Production Version in Standard Cost Estimate.

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Execute costing in app "Create Material Cost Estimate" (CK11N);
  2. Go to Qty Struct. tab;
  3. Check the Production Version;

Resolution

The strategies for selection of a production version in costing are as below:

  1. In mixed costing: according to procurement alternative settings;
  2. Production version displayed in material master Costing View 1 (Version Indicator);
  3. According to setting in Quantity Structure Control for BoM;
  4. If none of the above strategies is used, system will randomly pick a production version.

See Also

Production Version

Basic Master Data

Cost Estimate with Quantity Structure

Keywords

CK11N, Production Version, BOM, Costing, Cost Estimate, Quantity Structure, Master Data , KBA , CO-PC-PCP-WQS-2CL , Product Costing with Quantity Structure (Public Cloud) , CO-PC-PCP-WQS , Product Costing with Quantity Structure , How To

Product