3322368 - Error Message: "Labor resource assignment mandatory for project time recording on DD.MM.YYYY."

Symptom

When trying to approve time recording for Employee ABC the following error occurs "Labor resource assignment mandatory for project time recording on DD.MM.YYYY."

Environment

 SAP Business ByDesign

Reproducing the Issue

  1. Go to the Project Team work center.
  2. Access the Edit Time Sheet view under the Common Tasks section.
  3. Select the Employee ABC and select the Approve option.
  4. You receive an error message "Labor resource assignment mandatory for project time recording on DD.MM.YYYY."

Cause

It is not possible to post employee times when there is no Resource maintained. Labor resource assignment is required for Project Time Recording to calculate the project's internal costs based on labor resource cost rates.

Resolution

  1. In the Time Administration work center, in the Regular Tasks view, under Time Valuations, click Run Day Closure for One Employee.
  2. Specify the Employee ABC.
  3. Select the action Select Start Time Valuation
  4. Click Run to specify the valuation start date.

Note:

  • You can select the Backdated Labor Resource Changes checkbox to include backdated changes to assignments to a labor resource for the valuation run.
  • Please verify whether the assigned cost center has the valid labor resource created.

See Also

Time Valuation: Correction Run | SAP Blog

Keywords

Time Valuation, Labor Resource, Run Day Closure, Project Time Recording , KBA , labor resource , time valuation , run day closure , project time recording , SRD-HR-TLM , Time and Labour Management , Problem