3324819 - The budget tolerance limit of <XX>% for WBS element <XXXXXXXXX> has been reached.

Symptom

Below errors have been encountered during the approval of Purchase requisition.

  • The budget tolerance limit of <XX>% for WBS element <XXXXXXXXX> has been reached.
  • FCO_AVC_PS002.
  • Purchase requisition status not changed even though approval is completed.


Read more...

Environment

SAP S/4HANA Cloud Public Edition

Product

SAP S/4HANA Cloud Public Edition all versions

Keywords

FCO_AVC_PS002, tolerance, WBS, limit, budget, control, availability, project , KBA , MM-FIO-PUR-REL-2CL , Fiori UI for Purchasing Approval (Public Cloud) , FI-PRA , Predictive Accounting , Problem