Symptom
It's not clear how is scheduling agreement's validity date be considered during MRP run in S/4 HANA Cloud.
Environment
SAP S/4HANA Cloud.
Resolution
In S/4HANA Cloud, scheduling agreement could be used as a source of supply independently. Scheduling agreement's validity date (valid start and valid end) is used to determine whether schedule lines could be generated during MRP. When you run MRP, system checks scheduling agreement's validity date against delivery date. You can see more details in note 2268069. The behavior in S/4HANA Cloud is the same as in S/4HANA.
In special cases, like forward scheduling occurs, MRP checks scheduling agreement's validity date against rescheduling date minus GR processing time. See SAP Note 109380 for more details.
See Also
Keywords
MRP, Material Requirements Planning, MD01, MD01N, MD02, MD03, MD04, MD05, MD06, MD07, MD40, MD41, MD42, MD43, MDBT, ME38, source list, schedule agreement, contract, vendor, scheduling agreement, outline agreement, source, source of supply, Schedule MRP Run, app, S/4HANA Cloud , KBA , PP-MRP-PP-2CL , Procurement Proposal (Public Cloud) , PP-MRP-PP , Procurement Proposal , How To