3324847 - How is scheduling agreement's validity date be considered during MRP run

Symptom

It's not clear how is scheduling agreement's validity date be considered during MRP run in S/4 HANA Cloud.

Environment

SAP S/4HANA Cloud.

Resolution

In S/4HANA Cloud, scheduling agreement could be used as a source of supply independently. Scheduling agreement's validity date (valid start and valid end) is used to determine whether schedule lines could be generated during MRP. When you run MRP, system checks scheduling agreement's validity date against delivery date. You can see more details in note 2268069. The behavior in S/4HANA Cloud is the same as in S/4HANA.

In special cases, like forward scheduling occurs, MRP checks scheduling agreement's validity date against rescheduling date minus GR processing time. See SAP Note 109380 for more details.

See Also

  • SAP Note 109280 - Add. info: Validity source list/quota arrangement for MRP
  • SAP Note 2268069 - S4TWL - Simplified Sourcing

Keywords

MRP, Material Requirements Planning, MD01, MD01N, MD02, MD03, MD04, MD05, MD06, MD07, MD40, MD41, MD42, MD43, MDBT, ME38, source list, schedule agreement, contract, vendor, scheduling agreement, outline agreement, source, source of supply, Schedule MRP Run, app, S/4HANA Cloud , KBA , PP-MRP-PP-2CL , Procurement Proposal (Public Cloud) , PP-MRP-PP , Procurement Proposal , How To