3325401 - Planned quantity and requirement quantity are different for PIRs

Symptom

When comparing the value for planned quantity field in Change PIRs app and comparing with the value for requirement quantity field in Monitor Stock / Requirements List (MD04) app, you can see that the values are different.

Environment

SAP S/4HANA Cloud.

Reproducing the Issue

  1. Go to Monitor Stock / Requirements List (MD04) app
  2. Check the requirement quantity
  3. Go to Change PIRs app 
  4. Check the planned quantity
  5. The values are different 

Cause

Standard system behavior.

Resolution

PIRs can be consumed by different requirements.

For example, if you have a PIR of 100 and you have a sales order of 20 within the consumption period, you will only see 80 for the PIR in Monitor Stock / Requirements List (MD04) app, while you will still see the total quantity in Change PIRs.

The quantity will only be reduced in Change PIRs when you post a goods issue.

You can check in Change PIRs app -> 'Menu -> Environment -> Total Requirements', if the PIRs are being consumed by a requirement.

See Also

3127465 - Cannot find Display Total Indep. Requirements app

Keywords

Change PIRs, Display PIRs, Create PIRs, PIRs, App, MD61, MD62, MD63, MD04, Monitor Stock / Requirements List,  , KBA , PP-FIO-MRP-2CL , Fiori UI for Material Requirements Planning (Public Cloud) , PP-MP-DEM , Demand Management , PP-FIO-MRP , Fiori UI for Material Requirements Planning , PP-MP-DEM-2CL , Demand Management (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions