Symptom
- Doing project re-planning activities
- Need to assign unfinished WPs to a new Wave
- The new Wave has Sprint 1 defined and this new Wave is assigned to the new Release Number
- After assigning the Work Packages to the new Wave via the Mass Change App, user must assign the associated Work Items to the new Sprint
- When assigning the WIs in status In Development to the new Sprint 1, error is displayed:
Sprint is missing, Sprint is not yet Released, No link to Cycle
(The Sprint is already released) - When assigning the WI in status Successfully Tested to the new Sprint 1, error is displayed:
Sprint is missing
(The Sprint 1 is correctly linked to this New Wave 6.)
Read more...
Environment
- SAP Solution Manager 7.2
- Focused Build
Product
Focused Build and Focused Insights for SAP Solution Manager all versions ; SAP Solution Manager all versions
Keywords
KBA , SV-SMG-OST-FB-CM , Change Request Management , Problem