Symptom
There is an error "Deactivation not possible; ledger has postings after deactvatn date" or "The deactivation date in ledger is before the capitalization date" when customer tried to close a project in the APP Project Control.
Environment
SAP S/4HANA Cloud
Reproducing the Issue
- Use App: Project Control
- Select Project and change the processing Status to Close
- When saving, you receive error: "Deactivation not possible; ledger has postings after deactvatn date" or "The deactivation date in ledger is before the capitalization date"
Cause
The posting date is after deactivate date.
Resolution
The deactivate date must be after the posting date so please try to close the project after the posting date.
See Also
deactivate date, posting date, project control, deactivation not possible
Keywords
FAA_MD166, FAA_MD205 , KBA , PS-ST , Structures , Problem
Product
SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions