Symptom
While running Material Cost Estimate (CK11N) or Costing Run (CK40N), the error CK792 "No transfer price maintained for company code change" is being displayed.
Environment
SAP S/4HANA Cloud
Reproducing the Issue
- Run "Create Material Cost Estimate" (CK11N) or "Edit Costing Run" (CK40N);
- Check the error message CK792 "No transfer price maintained for company code change".
Cause
This error message is triggered when the system is not able to determine a procurement price from the Material Valuation Strategies.
Resolution
Adjust material valuation strategies in the costing variant so that a price can be determined. For example, you can enter a price in "Planned price 1" field in "Costing 2" tab in material master and add a valuation strategy to use "Planned price 1" to determine the price. This setting is done in Manage Your Solution / CBC System in SSCUI / Configuration Activity 104233 - "Define Costing Variants".
Note: If you have different valuation per plant, than you must check SSCUI / Configuration Activity 102608 - "Define Valuation Variants per Plant", since this one has higher priority.
See Also
Keywords
CK40N, CK11N, Costing Run, CK792, Transfer Price, Cross-Company, Material Valuation, Cost Estimate , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , CO-PC-PCP , Product Cost Planning , CO-PC-PCP-WQS , Product Costing with Quantity Structure , CO-PC-PCP-WQS-2CL , Product Costing with Quantity Structure (Public Cloud) , Problem