SAP Knowledge Base Article - Public

3330441 - Error CK792 "No transfer price maintained for company code change" during costing

Symptom

While running Material Cost Estimate (CK11N) or Costing Run (CK40N), the error CK792 "No transfer price maintained for company code change" is being displayed.

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Run "Create Material Cost Estimate" (CK11N) or "Edit Costing Run" (CK40N);
  2. Check the error message CK792 "No transfer price maintained for company code change".

Cause

This error message is triggered when the system is not able to determine a procurement price from the Material Valuation Strategies.

Resolution

Adjust material valuation strategies in the costing variant so that a price can be determined. For example, you can enter a price in "Planned price 1" field in "Costing 2" tab in material master and add a valuation strategy to use "Planned price 1" to determine the price. This setting is done in Manage Your Solution / CBC System in SSCUI / Configuration Activity 104233 - "Define Costing Variants".


Note: If you have different valuation per plant, than you must check SSCUI / Configuration Activity 102608 - "Define Valuation Variants per Plant", since this one has higher priority.

See Also

Edit Costing Runs

Create Material Cost Estimates

Material Cost Estimates - SAP Help Portal

Keywords

CK40N, CK11N, Costing Run, CK792, Transfer Price, Cross-Company, Material Valuation, Cost Estimate , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , CO-PC-PCP , Product Cost Planning , CO-PC-PCP-WQS , Product Costing with Quantity Structure , CO-PC-PCP-WQS-2CL , Product Costing with Quantity Structure (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions