3333472 - Not possible to change Pass On Lot Size for Costing Variant

Symptom

The option to change the value of "Pass On Lot Size" field is grey out in the SSCUI / Configuration Activity "Define Costing Variants".

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Access "Configure Your Solution" or your CBC System;
  2. Go to SSCUI / Configuration Activity "Define Costing Variants";
  3. Enter the Costing Variant;
  4. Under the tab Qty. Struct. the option to change the value of Pass On Lot Size field is grey out;

Cause

This happens because you are trying to change values in your Productive System, which is not possible. You can check this information in the "Redo in P" field, since this SSCUI / Configuration Activity is set as no, you won't be able to make changes in the Productive System.

Resolution

Make the changes in your Q System and then transport it to Productive.

See Also

Costing Variants

Configuration Environment of SAP S/4HANA Cloud

Keywords

Pass on lot size, Costing Variant, Material Valuation, SSCUI, Redo in P, Field grey out , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , CO-PC-PCP , Product Cost Planning , Bug Filed

Product

SAP S/4HANA Cloud Public Edition all versions