3334021 - Delivery Date not calculated according to planned delivery time (MRP area involvement) - ERP and S/4HANA

Symptom

There is no Source of Supply, info record etc. involved in the creation of a PR except Material Master.

Planned Delivery Time (PLIFZ) however does not come from Material Master where this value is usually filled (MRP 2 view/tab in Material Master MM03 -> MARC-PLIFZ).


Read more...

Environment

  • Materials Management (MM)
  • SAP ERP Central Component
  • SAP ERP
  • SAP enhancement package for SAP ERP
  • SAP enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA

Product

SAP ERP 6.0 ; SAP ERP Central Component all versions ; SAP S/4HANA 1610 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP S/4HANA 1909 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021 ; SAP S/4HANA 2022 ; SAP S/4HANA 2023 ; SAP enhancement package 1 for SAP ERP 6.0 ; SAP enhancement package 2 for SAP ERP 6.0 ; SAP enhancement package 3 for SAP ERP 6.0 ; SAP enhancement package 4 for SAP ERP 6.0 ; SAP enhancement package 4 for SAP ERP 6.0 on SAP enhancement package for SAP NetWeaver 7.0 ; SAP enhancement package 5 for SAP ERP 6.0 ; SAP enhancement package 6 for SAP ERP 6.0 ; SAP enhancement package 6 for SAP ERP 6.0, version for SAP HANA ; SAP enhancement package 7 for SAP ERP 6.0 ; SAP enhancement package 8 for SAP ERP 6.0

Keywords

ME51N, MRP 1, Planned Delivery Time, PLIFZ, MM, Material Master, MARC, MM02, MM03, PR, Delivery Date, MRP Area, no source of supply, PR without SoS , KBA , MM-PUR-REQ , Purchase Requisitions , Problem