3334021 - Delivery Date not calculated according to planned delivery time (MRP area involvement)

Symptom

There is no Source of Supply, info record etc. involved in the creation of a PR except Material Master.

Planned Delivery Time (PLIFZ) however does not come from Material Master where this value is usually filled (MRP 2 view/tab in Material Master MM03 -> MARC-PLIFZ).


Read more...

Environment

  • S/4HANA
  • ERP 6.0

Product

SAP ERP 6.0 ; SAP S/4HANA 1610 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP S/4HANA 1909 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021

Keywords

MRP 1, Planned Delivery Time, PLIFZ, MM, Material Master, MM02, MM03, PR, Delivery Date, MRP Area, no source of supply, PR without SoS , KBA , MM-PUR-REQ , Purchase Requisitions , Problem