Symptom
How to move unconsumed material of project stock to warehouse?
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project management work center
- Go to Project Stock order view
- Search for the relevant Project Stock order
- Choose edit
- Can see the Project Stock order is status "In Process"
- Order X quantity of material
- Consumed only Y quantity of material
- Expect(X-Y=Z), unconsumed Z quantity of material to move to warehouse (i.e. Here X,Y,Z are quantity of materials)
Cause
Since the satuts of the project stock order is "In Process", so the unconsumed quantities of the material remain in project.
Resolution
Once the Project Stock order is completed the remaining unconsumed quantities is being updated to the warehouse.
Keywords
Project stock order; Unconsumed material; Project , KBA , project stock order , unconsumed material , project , SRD-PRO-PMN , Project Management , How To
Product
SAP Business ByDesign all versions