SAP Knowledge Base Article - Public

3339283 - COSMAS not triggered for a new validity period created

Symptom

COSMAS not triggered for a new validity period created and cost center data not replicated to Successfactors. 

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Set up communication Scenario SAP_COM_0028 and follow the steps below.
  2. Open the app 'Manage Cost Centers'.
  3. Pick any cost center, click on 'Validity Period', new validity period.
  4. Create a new validity period starting from the next day (say tomorrow) till endless validity and save.
  5. No COSMAS Idoc is triggered.

Cause

This is expected behavior. 

COSMAS is triggered only for the current validity period. If you create a new validity period starting from say tomorrow, then there is no COSMAS triggered for the same.

Resolution

The validity period should be valid(active) at the moment, only then a trigger will be generated. So, creating a new validity period starting today or a previous date shall trigger a COSMAS update.

Keywords

COSMAS, cost center replication, trigger, SAP_COM_0028, scope item 1NL, Manage Cost Centers, validity period, time slices, Idocs, S4_PC, S4_1C , KBA , CO-OM-CCA-A , Master Data , CO-FIO-CCA-MD , Master Data , CO-FIO , Fiori UI for Overhead Cost Controlling , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions