Symptom

A Service Contract item was created, and the billing plan was set. The status of the item was also updated to Released. However, upon revaluing the revenue for the Service Contract item, no revenue is generated due to the absence of Planned Revenue.

Environment

SAP S/4HANA Cloud Public Edition

Cause

There is missing configuration.

Resolution

In the app "Event-Based Revenue Recognition - Service Documents," open the relevant Service Contract item and select "Revalue - Simulation Explanation." In the "Additional block 1" section, may see a message such as:

"Condition type AAAA: there is no assignment to a source."

To resolve this, update the configuration using SSCUI 102530. Once the configuration is corrected, run Revenue Recognition again for the object, and the revenue should be recognized.