Symptom
When searching for the activity to configure Scheduling Parameters for process manufacturing, you're not able to find in the CBC system.
"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."
Environment
SAP S/4HANA Cloud.
Reproducing the Issue
- Access CBC System
- Try to find Activity 'Define Scheduling Parameters for Process Industry'
- No results
Resolution
The correct name for the activity to configure Scheduling Parameters for process manufacturing is activity "Specify Scheduling Parameters".
For Production orders, the activity name is 'Define Scheduling Parameters for Production Orders'.
Keywords
Define Scheduling Parameters for Production Orders, Define Scheduling Parameters for Planned Orders, Define Scheduling Parameters for Process Orders, not find, not available, not showing. , KBA , PP-PI-POR-2CL , Process Order (Public Cloud) , PP-PI-POR , Process Order , Problem