SAP Knowledge Base Article - Public

3356309 - Customer Project (CP10) - Unable to assign Resourses

Symptom

Can't find the customer projects while using the Create Task function in the APP Manage My Timesheet.

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Go to the APP Manage My Timesheet
  2. Click the Create Task button
  3. Select the 'Other Accounting Object' option
  4. Can't find the customer projects in the WBS Element selection

Cause

standard behavior

Resolution

  • Please use 'Unstaffed Project' for the customer projects
  • Please use 'Other Accounting Object' for the enterprise projects 

See Also

'Manage My Timesheet', 'Unstaffed Project', 'Other Accounting Object', 'enterprise project'

Keywords

KBA , CA-TS-S4 , Cross Application Timesheet in S/4HANA , How To

Product

SAP S/4HANA Cloud 2302