Symptom
You want to calculate overhead for project with app Run Overhead Calculation - Actual.
However, no result was calculated.
Environment
SAP S/4HANA Cloud Public Edition
Cause
Please check the master data for the project to see whether it's assigned to a plant.
Resolution
If the project is not assigned to plant, you need to assign it to the plant and then calculate again.
Since in costing sheet, the calculation is done on plant level.