3358928 - Planning calendar not work if individual segment involved during MRP run.

Symptom

Make-to-order or Make-to-project scenario is used.
However, planning calendar is not considered by MRP.


Read more...

Environment

  • SAP ERP Production Planning (PP)
  • SAP ERP Release Independent
  • SAP ERP Central Component Release Independent
  • SAP Enhancement package for SAP ERP Release Independent
  • SAP Enhancement package for SAP ERP, version for SAP HANA Release Independent
  • SAP S/4HANA, on-premise Release Independent
  • SAP ERP Fiori UI for Material Requirements Planning Release Independent

Product

SAP ERP 6.0 ; SAP ERP Central Component 6.0 ; SAP Fiori apps for SAP ERP all versions ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021 ; SAP S/4HANA 2022 ; SAP enhancement package 2 for SAP ERP 6.0 ; SAP enhancement package 3 for SAP ERP 6.0 ; SAP enhancement package 4 for SAP ERP 6.0 ; SAP enhancement package 5 for SAP ERP 6.0 ; SAP enhancement package 6 for SAP ERP 6.0 ; SAP enhancement package 7 for SAP ERP 6.0 ; SAP enhancement package 8 for SAP ERP 6.0 ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

planning calendar, lot size, make-to-project, make-to-order, OMI4,TERBV,LGKND , KBA , PP-MRP , Material Requirements Planning , Problem