Symptom
When looking at the Project Plan Value of a specific Project, the Plan Cost shows 0 in Materials tab.
Environment
SAP Business ByDesign
Reproducing the Issue
-1-
Work CenterProject Management.
Projects View.
Search, Open and View All the Project ABC.
Under Project Plan > Gantt Chart >Materials, you have maintained the Materials XYZ and selected the option "From Stock".
-2-
Open the Master Data of Material XYZ.
Select the Valuation Tab.
You have maintained Warehouse as a Business Residence with a positive cost maintained; you expect this cost to be visible in the Project Plan Value.
-3-
Work Center Cost and Revenue.
Projects view.
Search for Project ABC > View Planned Value related to the task which contained the Material XYZ.
Select Materials sub-tab, the Planned Cost shows a value of 0 instead of what is maintained under Material Master Data.
Cause
Upon the creation of the Project ABC, under Ship From, you have not selected Warehouse.
Resolution
Work Center Project Management
Project View
Search, Open and View All the Project ABC
Select Project Plan tab > Gantt Chart, under Ship From select Warehouse (or the same Business Residence maintained in Product Master Data) and Save.
After doing so, the correct value will show up in Work Center Cost and Revenue.