Symptom
When a MTO process is created with a sales quotation, the sales quotation number instead of the sales order number is used as reference in the planned order.
*Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Environment
SAP S/4HANA Cloud Public Edition
Cause
This is caused by system configuration.
Resolution
- This behaviour is controlled by the requirement type.
-
Currently the Requirement Type is determined using the Material Master Strategy (MRP 3 Tab) first which is currently B6 for the Demo Material FG228 and will result in Requirement Type BB6.
- See Quotation Procurement Tab below:
- In order to have the Sales Order as as the referenced document for the Planned Order this needs to be set/determined to S46. For this the SSCUI 105120 "Determine Requirement Type by Item Category and MRP Type" can be adjusted:
-
The current blank standard content for Src evaluates to 0 which means the Material master strategy is considered first.
- By setting it to 1 - Item Category and MRP Type the underlying table of the SSCUI is taken for the Requirement Type determination and evaluates to S46.
-
With this the Planned Order should reference to the Sales Order it was created for.
Keywords
MTO, make to order, sales order, planned order, quote, order, s/4HANA Cloud, public cloud , reference, reference number, reference document , KBA , SD-SLS-SO-MO-2CL , Make-to-order, assembly order (Public Cloud) , Problem