Symptom
WBS element not found in the F4 help while doing Budget Transfer using the app 'Manage Budget Document - Projects'.
Environment
SAP S/4HANA Cloud
Resolution
In the app 'Manage Budget Documents - Projects', all the budget documents like budget transfer, budget supplement or budget return, can be created only between the lower level WBS elements that belong to the same company code and not at the project definition level. Hence, in order to transfer budgets make sure there are lower level WBS elements created for the project.
Keywords
Budget transfer, Manage budget document - projects, wbs element, F5342, budget supplement, budget return, S4_PC, S4_1C , KBA , PS-COS-BUD , Budget , How To