3365454 - Overhead is not calculated in standard cost estimate

Symptom

You create standard cost estimate, and found the overhead is not calculated.

Environment

SAP S/4HANA Cloud Public Edition

Cause

1. The costing sheet configuration was created with inconsistent data. The root cause is not known.

2. There is no overhead key assigned to the material master.

Resolution

1. Workround:
create new costing sheet by copying 0162EP or any existing standard delivered costing sheet.
create new base with different name, same attributes
replace base with newly created base in new costing sheet
change costing sheet assignment for your valuation variant with new costing sheet

For the wrong costing sheet, if you know how to reproduce (how it was created), please raise new case to SAP for further analysis.
2. Add overhead key and test again.

Keywords

Costing Sheet, cost estimate, CK11N, overhead, blank, zero, no value, Actual Overhead Calculation, Run Overhead Calculation. , KBA , CO-OM-OPA-2CL , Overhead Orders (Public Cloud) , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem