Symptom
When setting the stage from 'Closed' to 'Completed' in Customer Projects, the following message is encountered: "System status CLSD is active (WBS XXXX.0.1)". An exception message is also raised subsequently.
Environment
- Sales and Distribution (SD)
- Enterprise Portfolio and Project Management (EPPM)
- SAP S/4HANA Cloud CE2308
Cause
Profitability segment number (PAOBJNR) domain was changed in 2308.
Resolution
A correction is planned for hotfix collection 4 (HFC04). See schedule for more details.
In the meantime, a workaround is available:
- Open the "Closed" Project.
- Go to Edit mode and navigate to the "Billing" section.
- Make a dummy change; i.e. such as entering a value for the customer reference.
- Navigate back to the section "Information" of the project. In the Data Loss Warning Popup ensure that the change is saved.
Keywords
WBS, F0719, Plan Customer Projects, /CPD/SC_PROJ_ENGAGMNT_MAINT_SRV, SAP_BR_PROJ_MANAGE_COMM, Project manager, CUST_PROJECT_H, upgrade, 2302, CE2302, SO01, PS,Enterprise Portfolio and Project Management, EPPM , KBA , SD-SLS-2CL , Sales (Public Cloud) , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem