Symptom
When PR is created by MRP run, the delivery date is calculated as expected.
However, when PR is converted from a planned order, the delivery date is different compared to MRP created PR.
Read more...
Environment
- SAP ERP Production Planning (PP) Release Independent
- SAP ERP Release Independent
- SAP ERP Central Component Release Independent
- SAP Enhancement package for SAP ERP Release Independent
- SAP S/4HANA, on-premise Release Independent
- SAP Fiori for SAP ERP Release Independent
- SAP Fiori for SAP S/4HANA Release Independent
- SAP S/4HANA Cloud Private Edition Release Independent
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP Fiori for SAP ERP all versions ; SAP Fiori for SAP S/4HANA all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions
Keywords
MD14, delivery date, planned delivery time, PDT, convert planned order to PR. , KBA , PP-MRP , Material Requirements Planning , Problem