Symptom
When trying to create a new project in transaction code CJ20N, project finish date (PLSEZ) is filled automatically. This behavior is not expected.
Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Read more...
Environment
- SAP ERP Project system (PS)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
PLSEZ, schedule, finish date, start date , KBA , PS-ST-DEF , Project Definition , PS-ST-WBS , Work Breakdown Structure , PS-ST , Structures , Problem