3383233 - How the offsetting days and planned start are calculated in FCLOCOC using factory calendar

Symptom

It is not clear how the offsetting days and planned start dates are calculated when using factory calendar and scheduling a task on a specific date in Financial Closing Cockpit t-code, like FCLOCOC.

Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.


Read more...

Environment

  • SAP ERP
  • SAP enhancement package for SAP ERP
  • SAP enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA Finance
  • SAP S/4HANA
  • SAP Financial Closing cockpit

Product

SAP ERP all versions ; SAP Financial Closing cockpit all versions ; SAP S/4HANA Finance all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

Calendar, FCLOCOC, Offset Days, SCAL, Task List, Key date, Reference date, Task template, factory calendar, offset, offsetting, calculation, FCLOCO, FCLOCOT, Financial closing clockpit , KBA , CA-GTF-FCC , Financial Closing cockpit Add-on , How To