Symptom
- Requirement is to set up a CK40N batch job that can run automatically
- SAP note 3023846 has been followed
- However during the automatic run of job, message CK075 "Planning date is in the past -> cost estimate cannot be saved" occurred
- The expected behavior is to set up a batch job with a dynamically changing costing date, without the need to manually change dates every time.