Symptom
The customer want to set up CK40N batch job which can run automatically, note 3023846 has been followed.
However during the automatic run of job, message CK075 "Planning date is in the past -> cost estimate cannot be saved" occurred.
The expect behavior is to set up a batch job with dynamically change of costing date (which means without manually change dates every time).
Read more...
Environment
- S/4 HANA
Product
Keywords
CK40N, automaticall, automatically run, SAPRCK_COSTING_RUN_COPY, SAPRCK_COSTING_RUN_START_STEPS, CK075, planning date is in the past -> cost estimate cannot be saved , KBA , CO-PC-PCP , Product Cost Planning , Problem