Symptom
- Requirement is to set up a CK40N batch job that can run automatically
- SAP note 3023846 has been followed
- However during the automatic run of job, message CK075 "Planning date is in the past -> cost estimate cannot be saved" occurred
- The expected behavior is to set up a batch job with a dynamically changing costing date, without the need to manually change dates every time.
Read more...
Environment
- S/4 HANA
Product
SAP S/4HANA 2020
Keywords
CK40N, automatical, automatically run, SAPRCK_COSTING_RUN_COPY, SAPRCK_COSTING_RUN_START_STEPS, CK075, planning date is in the past -> cost estimate cannot be saved , KBA , CO-PC-PCP , Product Cost Planning , Problem