Symptom
Overhead amount is different between order planned cost and material cost estimate/actual cost.
Environment
SAP S/4HANA Cloud
Cause
The order planned cost is calculated with more detailed granular.
Resolution
For material cost estimate, it only considers the calculation base account, to calculate the overhead amount on the percentage defined in costing sheet.
For order planned cost/actual cost, it determines the activity type, object ID, and lot size independent indicator, and group the values together as a sum value.
During the calculation, there could be rounding difference.
Example,
Order planned cost:
Cost Element | LotSizeIndependent | Value | Subtotal | Rate | Value |
Total(rounded) |
|
Line1 | 100000 | 666 | 10% | ||||
Line2 | 100000 | 1000 | 1666 | 10% | 167 | ||
Line3 | 100000 | X | 167 | 167 | 10% | 17 | 184 |
Material cost estimate:
(666+1000+167)x10% = 183 (rounded)
To adjust the rounding variance, you can use app Reassign Costs and Revenues to post to the same account.
Keywords