3393607 - MRP doesn't plan PIR in manually reorder point

Symptom

When you set manually reorder point, MRP doesn't create replenishment to fulfill the PIR in MD04. And total available quantity is below reorder point.

Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental. 


Read more...

Environment

  • SAP ERP Production Planning (PP) 
  • SAP ERP  
  • SAP ERP Central Component  
  • SAP Enhancement package for SAP ERP  
  • SAP Enhancement package for SAP ERP, version for SAP HANA  
  • SAP S/4HANA, on-premise Environment 

Product

SAP ERP Central Component for discrete industries all versions ; SAP ERP all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

MRP, Reorder point, Manually, Requirement, Planned independent requirement, PIR, OMDQ , KBA , PP-MRP , Material Requirements Planning , Problem