SAP Knowledge Base Article - Public

3393814 - PSM Release for the BO project Task material period plan

Symptom

You require the PSM Release for the BO project Task material period plan 

Environment

SAP Business ByDesign

Reproducing the Issue

  1. 1. Go to Project Management - Project
  2. Select any Project -PQR(PQR refers to the Project)
  3. Open the Project Plan
  4. Choose Project Task ID: DEF(DEF refers to the Project Task Id) in the tab Material ID: 
  5. When opening the Period Plan, created multiple period plans and would like PSM release for this Business Object.a  

Cause

The respective for Business Object of Project Task material period plan is already in PSM release state.

Resolution

You can create a PDI/Custom solution with this functionality for Business enhancement. 

Business Object      PRO_PROJECT
Node                 TASK_MAT_PERIOD_PLAN

Keywords

KBA , AP-PRO , Project Processing , Problem

Product

SAP Business ByDesign all versions