3396628 - There is already a released cost estimate with costing variant - SAP S/4HANA Cloud Public Edition

Symptom

There are several ledgers.
When trying to make setting for Marking Allowance for material standard cost estimate, in the first step, it is allowed for one of the ledger (for example, ledger 0L), then the costing run is done and cost estimates is released.

Currently, it is noticed cost estimate for ledger 2L is still not created, and need to allow the same variant/version for ledger 2L.
Got error for example "There is already a released cost estimate with costing variant PPC1".


Read more...

Environment

SAP S/4HANA Cloud Public Edition

Product

SAP S/4HANA Cloud Public Edition all versions

Keywords

Cost estimate, CK40N, allowance, costing variant, ledger , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.