Symptom

Unit of Measure to be changed from Hours to Days in Project ABC 

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Project Management work center
  2. Go to Projects view
  3. Search for Project ABC and open 
  4. Navigate to Work sub tab, we see that Unit of Work is showing as h (hours).

Cause

There is no cause for this, as this is a consulting query.

Resolution

We can change the Unit of Measure (Work) by following the below steps:

  1. Go to Project Management work center
  2. Go to Projects view and search for Project ABC
  3. Under Project Plan tab, Project Settings subtab, change the Unit of Work from Hours to Working Day(s) and save