Symptom
Unit of Measure to be changed from Hours to Days in Project ABC
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project Management work center
- Go to Projects view
- Search for Project ABC and open
- Navigate to Work sub tab, we see that Unit of Work is showing as h (hours).
Cause
There is no cause for this, as this is a consulting query.
Resolution
We can change the Unit of Measure (Work) by following the below steps:
- Go to Project Management work center
- Go to Projects view and search for Project ABC
- Under Project Plan tab, Project Settings subtab, change the Unit of Work from Hours to Working Day(s) and save
Keywords
How to Change the Unit of Measure in a Project , Unit of Work in Project , KBA , SRD-PRO-PMN , Project Management , How To
Product
SAP Business ByDesign 2311