3399509 - MRP: Discontinuation function usage restrictions.

Symptom

It is observed MRP run failed to transfer shortages from the discontinued part to follow-up material in below cases:

  • No discontinuation at storage location or subcontracting MRP area level.
  • No discontinuation for order reservation, sales order, planned independent requirement.
  • No discontinuation for subcontracting dependent requirement.
  • No discontinuation in reorder point planning scenario even if stock quantity is lower than reorder point.
  • No discontinuation happens when using t-code MD11 or MF50.




Read more...

Environment

  • SAP ERP Production Planning (PP) 
  • SAP ERP 
  • SAP ERP Central Component 
  • SAP Enhancement package for SAP ERP 
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise
  • SAP S/4HANA Cloud Private Edition 

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

discontinuation; MRP area; MARC-KZAUS , KBA , PP-MRP , Material Requirements Planning , Problem