Symptom
It is not possible to change the Profit Center of a project in app "Project Control - Enterprise Projects".
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open app "Project Control - Enterprise Projects";
- Select a project to open its details;
- Click on Edit;
- Notice that the Profit Center field is not editable.
Cause
This is the standard system behavior when the project has already been Released.
Resolution
It is not possible to change the Profit Center of a project using app 'Project Control - Enterprise Projects' once the project has the Processing Status defined as Released.
As a workaround, it is possible to change the Profit Center using app "Manage Organizational Changes".
Be aware that Scope Item 4PG must be activated in the system, in order to access app "Manage Organizational Changes". This scope item isn't standard and isn't activated by default.
See Also
Further information can be found in the following documentation:
Keywords
s/4hana cloud, f3215, proj-prctr, project, project control, enterprise projects, edit, change, profit center, display, read-only, processing status, created, released, manage organizational changes, 4pg , KBA , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , PPM-FIO-2CL , Please use PPM-SCL* , PPM-SCL-STR , Project Structure (Public Cloud) , How To