3405550 - Rescheduling horizon will be taken from plant if it is set 0 for MRP group.

Symptom

Rescheduling horizon is maintained 0 day for MRP group.
It is observed Rescheduling horizon didn't pick value 0 but took the value maintained for plant.


Read more...

Environment

  • SAP ERP Production Planning (PP)
  • SAP ERP Release Independent
  • SAP ERP Central Component Release Independent
  • SAP Enhancement package for SAP ERP Release Independent
  • SAP Enhancement package for SAP ERP, version for SAP HANA Release Independent
  • SAP S/4HANA, on-premise Release Independent
  • SAP ERP Fiori UI for Material Requirements Planning Release Independent

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP Fiori apps for SAP ERP all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

OMDW, rescheduling horizon, MRP group. , KBA , PP-MRP , Material Requirements Planning , Problem