Symptom
You want to close the change project after a successful merge changes.
Environment
- SAP Business ByDesign
- SAP Cloud for Customer
Reproducing the Issue
- Go to Business Administration work center.
- Go to Implementation Projects view.
- You will see that change project remains with status as "Merged" instead of closed.
Resolution
After the merged changes, you have to close the activity Close Project.
- Go to Business Configuration work center.
- Go to Implementation Projects.
- Select the project with status as "Merged" and open activity list.
- In the Go Live tab you will see that the activity "Close Project" remains opened.
- Close the activity to get the project status as closed.
Keywords
Merge changes, Change Project, Close Change Project, Merged Status , KBA , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , How To
Product
SAP Business ByDesign all versions ; SAP Cloud for Customer core applications all versions