Symptom
Different availability dates in ECC and PPDS for purchase requisition, purchase order or stock transfer.
Availability date is not the same in MD04 and /SAPAPO/RRP3 for external procurement orders.
Read more...
Product
SAP S/4HANA all versions
Keywords
PR, PO, STR, STO, mismatch in dates, rescheduling, GR processing time, goods receipt end date, duration, calendar planning, resource planning, availability time, ELDAT, ELUHR, UNLD, UNLOAD , KBA , SCM-APO-INT-PUR , Purchasing / Purch. Req. and Order, Transfer Order , Problem