Symptom

Project status is 'Completed' in APP 'Plan Customer Project', however, posted revenue is not cleared when running revenue recognition.

Environment

SAP S/4HANA Cloud Public Edition

Cause

Only the period after 'Techinical completion' date can clear the revenue.

Resolution

Kindly choose the correct period for revenue recognition run,
for example, if status 'technically completed' is active for date 01/31/2024,
then revenue can only be cleared when you run revenue recognition in period 01/2024.

Keywords

revenue recognition, techinical completion, TECO, period end closing, project status, completed. , KBA , CO-PC-OBJ-EBR , Event-Based Revenue Recognition , Problem

Product

SAP S/4HANA Cloud 2308